Recent Work on Losses
Muon1 modified to count lost particle
energies
For a 4MW p+ beam:
35kW deposited in S1 (r=10cm)
Large >1kW amounts deposited up to S5
Added “collimators” to the simulation
Decreases losses to 10’s of watts in all but S1
and S2
S1 needs enlarging to accommodate an entire
Larmor rotation
Consistent target-area layout is needed